Same sprint. A different story each day.
Compare time elapsed, completed work and scope changes at Day 1, Day 5 and Day 10. A completion percentage only makes sense when you know which plan it measures.
Understand sprint health →- Original commitment
- 40
- Added scope
- +8
- Removed scope
- −2
- Completed
- 18
- Remaining work
- 28
- Carryover at sprint start
- 12
Completed / current scope: 18 / 46 issues.
Half the time has elapsed, but scope has grown by 6 issues. Completion alone hides that change.
Carry-in is included in the original commitment. Time is context, not a linear delivery forecast.